Sargent & Lundy provided owner’s engineer and design reviews of the project’s solar photovoltaic (PV), battery energy storage system (BESS), substation, and generation interconnect-lines.

Eleven Mile Solar Center

Sargent & Lundy provided owner’s engineer and design reviews of the project’s solar photovoltaic (PV), battery energy storage system (BESS), substation, and generation interconnect-lines.

Client

Ørsted

Location

Pinal County, Arizona

Milestones

  • Project start: August 2022
  • Commercial operation: October 2024

Sang Gang

Vice President

312-269-6902

Email

Project Details

Client

Ørsted

Location

Pinal County, Arizona

Milestones

  • Project start: August 2022
  • Commercial operation: October 2024

Sang Gang

Vice President

312-269-6902

Email

300 megawatt solar PV and AC-coupled 300 MW / 1200 megawatt-hour BESS project


Project Highlights

  • Co-developed battery energy storage system (BESS) technical specifications.
  • Conducted holistic reviews of solar PV, co-located AC-coupled BESS, substation, and generation interconnect-line designs.
  • Project represents a $1 billion investment and generates enough energy to power nearly 65,000 homes a year.

Project Description

Ørsted contracted Sargent & Lundy as owner’s engineer for the Eleven Mile project’s 300 megawatt (MW) solar PV and AC-coupled 300 MW / 1200 megawatt-hour BESS located in Pinal County, Arizona. The project started construction in 2023 and began commercial operation in 2024.

Project Scope

Sargent & Lundy performed owner’s engineer BESS technical specification development and subsequent design reviews of the project’s solar PV, BESS, substation, and generation interconnect-line designs for the Eleven Mile project. Sargent & Lundy’s objective was to assess engineering, procurement, and construction (EPC) design deliverables for code compliance, prudent industry standards and best practices, operational safety considerations, performance, reliability, constructability, and the project specific technical specifications. The firm also performed detailed reviews of the power purchase agreement (PPA) and permitting requirements.

Sargent & Lundy’s scope of work included:

  • Review of major equipment vendor submittals.
  • System design review of solar PV, co-located AC-coupled BESS, substation, and generation interconnect-line designs (e.g., fire protection, electrical, civil, and structural).
  • Electrical studies review.
  • Identification of value engineering opportunities and plant performance optimization.
  • Commissioning and testing plans review.

Read more about our consulting & planning services.