HomeFossil PowerNuclear PowerPower DeliveryGlobal Energy ConsultingRenewable & Alternative EnergyNews & PublicationsAbout Us
Power Delivery

Construction Management

American Transmission Company
Central Portfolio
As part of an EPC project team led by Kenny Construction Company, Sargent & Lundy is performing engineering for a group of 345-kV and 115-kV substations located in the Wausau, WI area. Many of the projects are associated with the addition of 500 MW of generation at the Weston Generating Station, scheduled to come on line in 2008. Sargent & Lundy's scope of work includes support for Public Service Commission and Department of Natural Resources permits, as well as design of new and upgraded facilities.
East Portfolio
Sargent & Lundy was selected by ATC as the engineering firm for their East Portfolio, which includes Milwaukee and the southeastern region of Wisconsin. The work includes a broad range of services for new and upgraded 69-kV and 138-kV substations. S&L is also performing construction coordination, quality control surveillance, and commissioning services for a number of ATC projects.
Calpine Riverside Generating Station Interconnection
Sargent & Lundy performed complete engineering and design for the interconnection of an independent power project generating station to the American Transmission Company system as part of an EPC team. This included a 138-kV switchyard and transmission tie line. Our scope of work included electrical testing and commissioning services. Sargent & Lundy was the engineering subcontractor to M. J. Electric of Iron Mountain, MI for this EPC contract. The project was completed in 2003.
City of Anaheim Public Utilities Department
Sargent & Lundy is supporting the City of Anaheim, CA in a major upgrade/expansion of its transmission and distribution system. Sargent & Lundy is serving as owners engineer and construction manager for a series of gas-insulated substation (GIS) projects located in both enclosed and outdoor facilities. These projects include the following:
Park Substation

69 kV/23.8 kV indoor/underground GIS, placed in-service in 2006.

Project Profile: Park Substation Project
Lewis - Vermont Project
230kV/34kV GIS in an open-air substation and a 230-kV transmission line, scheduled to be completed Fall 2007.
Anaheim Substation
69 kV/13.8 kV indoor GIS located in downtown Anaheim, scheduled to be completed Spring 2008.
Colorado River Commission

The River Mountains Project consists of two 230-kV transmission lines in the vicinity of Boulder City, Nevada. The project was developed jointly by the Colorado River Commission (CRC), Nevada Power Company (NPC) and the Southern Nevada Water Authority (SNWA). The transmission lines, which extend approximately 30 miles from the Western Area Power Administration Mead Substation to CRC's Newport Substation and NPC's future Equestrian Substation, include rebuilds of two of NPC's existing 69-kV transmission lines as underbuilt circuits. The lines were constructed on lattice steel towers and tubular steel poles. Sargent & Lundy performed construction inspection services for this project. Completed in 2001.

Project Profile: River Mountains Project - New 230-kV Transmission Line With Diverse Engineering and Construction Constraints
Exelon
ComEd

Working together with Exelon's Contractor of Choice (COC) teams led by Kenny Construction Company and Infrasource, S&L is performing engineering for a number of 138-kV and 345-kV substations throughout northern Illinois. In addition to engineering, S&L coordinates the electrical testing and commissioning of each substation and performs construction quality control services. As Exelon's Engineer of Choice, S&L is coordinating nuclear plant switchyard modifications during refueling outages.

In addition, S&L and the COC team has been working on a series of major, enclosed substation projects for the ComEd in Chicago's central business district.

Project Profile: Chicago Optimization Projects
Project Profile: Madison and Ohio Substation Projects
Nevada Power Company
Our staff performed engineering, permitting support and other services for a number of 69-kV and 230-kV transmission lines in the Las Vegas area. This included the 13-mile Nellis-Apex and Apex Relocation 69-kV lines, which replaced deteriorated wood-pole structures with light-duty steel poles. The Del Webb 2000 project involved the relocation of three existing 230-kV lines for a major residential development. The Arden- Northwest project included 17 miles of quad-circuit line. The McCullough-Arden #2 transmission line consisted of 15 miles of 230/138-kV quad-circuit line and the Crystal-Harry Allen project included approximately 10 miles of double-circuit 230-kV lines. S&L has also provided construction quality control surveillance personnel for a number of Nevada Power transmission line projects.
Centennial Project
The 29-mile Harry Allen - Northwest 500-kV Transmission Line, which was a component of Nevada Power's Centennial Project, was designed by Sargent & Lundy. This line was constructed on single-circuit and double-circuit steel poles and lattice towers. This project was completed in 2003. Sargent & Lundy also performed structural analysis of 500-kV tower designs for use on the Northwest - Mead segment of this project. We evaluated existing tower designs for use with Nevada Power's conductors, loading criteria and tension limitations. This work was completed in 2004.
Harry Allen - Mead

Sargent & Lundy is performing construction management services for this 500-kV transmission line project, including monitoring of compliance with project permits and grants of easements from federal agencies and inspection of access road construction, foundation installation, tower assembly and erection, wire stringing. The route crosses rugged desert terrain, presenting challenges to structure access and foundation installation. Our construction management team is on-site throughout the project duration and includes personnel experienced in all aspects of transmission line projects.

Project Profile: Harry Allen-Mead Project
New York Power Authority

Connecting 11 Peaker Plants at 7 New York City Sites

Project Profile: In-City Generation Project
PacifiCorp
Wasatch Front Quantum Leap Projects

As part of an EPC team, Sargent & Lundy is performing complete engineering, construction, quality assurance, and commissioning services for a major upgrade of the transmission and distribution system in the PacifiCorp Salt Lake City region. The prime contractor is Kenny Construction Company of Chicago, IL.

The transmission scope of work includes seven transmission projects involving a total of approximately 50 miles of 138 kV line, plus an additional 15 miles of line to accommodate the new and upgraded substation projects. The substation scope of work includes 12 new 138/12.5-kV substations and upgrades of 19 existing substations. In addition to engineering, Sargent & Lundy's scope of work includes construction quality assurance and testing and commissioning services.

The majority of the projects were completed to meet summer peak loads in 2003 and 2004 and the remaining projects completed in 2005.

Project Profile: Quantum Leap
Richmond Power & Light Company
Sargent & Lundy completed engineering for the rebuild of the Whitewater - Johnson Street 138-kV Transmission Line, increasing the load transfer capacity of the line and replacing aging wood structures with new steel poles in 2004. Sargent & Lundy also performed construction quality control surveillance for this project, located in northeastern Indiana.
Sierra Pacific Power Company
Sargent & Lundy provided field quality assurance and inspection services for two major 345-kV transmission line projects in Nevada for Sierra Pacific Power Company. Sargent & Lundy's scope of work for both projects included providing a Quality Assurance Supervisor and team of construction engineers to monitor the construction work for compliance with the engineering drawings and specifications, material coordination, and contract administrative functions. The Sargent & Lundy Quality Assurance Team monitored construction activities from clearing and access road construction through clean-up and restoration.
Falcon-Gondor Project
The Falcon-Gondor project included a 180-mile 345-kV transmission line constructed on tubular steel H-frame structures and a 345-kV expansion of the existing 230-kV Gondor Substation. The project is located in central Nevada and was completed in 2004.
Alturas Project
This project consists of approximately 160 miles of new 345-kV transmission line, two new 345-kV substations, and two communication repeater sites, located in northeastern California and western Nevada. The Alturas Intertie connects the Sierra Pacific system to the Bonneville Power Administration transmission. This project was placed in service at the end of 1998.