San Carlos Solar PV Projects

Sargent & Lundy is the independent engineer to support financing of a portfolio of solar projects


SAN CARLOS SOLAR PV PROJECTS
Negros Island, The Philippines
Solar Project Financing Support
Client: International Finance Corporation

  • 85 MW total, four sites
  • First site began commercial operation in 2014

Sargent & Lundy was engaged as the independent engineer to support financing of the projects. Work began in March 2014 and is ongoing. Staff from the Sargent & Lundy project team is performing quarterly site visits.

Project Scope:

  • Review of the plant design and solar technology
  • Balance-of-plant design review
  • Grid interconnection review
  • Site suitability review
  • Independent estimation of solar resource and projected energy production
  • Technical review of project contracts
  • Construction and completion monitoring
  • Social and environmental review
  • Financial model review

For more information about our services, please see our Renewable Energy page.

Matthew Thibodeau

Vice President

312-269-6894

Email

About

Matthew has managed renewable energy, utility planning, and grid modernization projects in more than a dozen countries.