Hillabee Energy Center Combined-Cycle

From mothballed project to 740 MW of reliable power


Hillabee Energy Center Combined-Cycle
Tallapoosa County, Alabama
Client: Calpine Corporation (original project)

Print This Page


Project Highlights:

  • Combined Cycle / 740 MW / 2X2X1 / Natural Gas
  • Constellation Energy (restarted)
  • Fuel: Natural gas
  • Size: 740 MW
  • Configuration: 2x2x1
  • CT Supplier-Type: SWPC 501G

Project Description:

Sargent & Lundy initially began work on the natural gas-fired Hillabee Energy Center project in 2001. Engineering scope was for all detailed engineering and design, including, site development, civil design, design criteria, piping and instrumentation diagrams, piping physical drawings, natural gas yard, power and control cabling, structural steel and foundations, procurement support, onsite field engineering support during construction, as well as construction/startup support.

The Hillabee project uses Siemens-Westinghouse 501G combustion turbines in a 2x2x1 configuration and incorporates a wet cooling system with single-row counterflow cooling tower. Makeup water is potable-quality from nearby Alexander City via a newly installed water pipeline. The project was suspended by Calpine in spring 2003 with construction at +60% complete and engineering substantially complete.

In 2008, Constellation Energy acquired the unfinished plant and authorized Sargent & Lundy to restart the engineering effort, with commercial operation achieved in 2009. The 740‑MW Hillabee Energy Center joined Exelon Power’s fleet in 2012 as part of the Exelon/Constellation merger.


Schedule Milestones:

  • 2001 - Begin engineering and design
  • 2003 - Construction postponed
  • 2008 - Project restarted
  • 2009 - Commercial operation

Read more about our energy & industrial services.