Sargent & Lundy

Sargent & Lundy to Present on Urban Project at EUCI Underground Transmission Conference

January 21-22, 2016, in Newport Beach, California

December 18, 2015 – Sargent & Lundy’s Dennis O’Reilly will present “A Case Study for Installation of a 115-kV Underground Transmission Line in a Residential and Commercial Area” at 3:00 p.m. on January 21, 2016.

The presentation will include a discussion of the data collection and analysis techniques used to permit, design, and install a double circuit 115-kV underground transmission line in an urban area.  The transmission line crossed under a light rail line, adjacent to a Superfund site and a hospital emergency room entrance, in addition to the services typically installed under city streets in urban areas.

Todd Hanssen

Senior Vice President




Todd brings 25 years of experience in the design of power generation and transmission projects and is currently the director of power transmission construction services.